Marjan Beach to open first phase in 2 months; development to take 10 years

Marjan Beach, a 10‑year mixed‑use waterfront district on Marjan Island, is poised to complete its first phase in two months. The project, led by Group CEO Abulla Al Abdouli, involves major developers such as Wasl, Omniyat, and Beyond, and includes plans for residential, commercial, and cultural pre…

Marjan Beach, a sprawling waterfront district on Marjan Island in Ras Al Khaimah, is on the cusp of completing its first phase of construction. Group CEO Abulla Al Abdouli announced that earthwork for the initial stage will be finished within the next two months, marking a significant milestone in the decade‑long development plan.

What’s Happening Now?

According to Al Abdouli, the first phase of Marjan Beach’s earthwork— the process of removing soil and preparing the site for building—will wrap up in the coming weeks. The announcement was made during the Arabian Travel Market, where Marjan also unveiled a new virtual platform, the Marjan Digital Universe, allowing investors to explore the master developer’s projects online.

Key players in the project, including Wasl, Omniyat, and Beyond, have secured plots and sites within the beach development. These companies are set to contribute to the mixed‑use landscape that will feature premium homes, hospitality venues, cultural spaces, and lifestyle experiences.

The Bigger Picture: A 10‑Year Masterplan

Marjan Beach is part of a broader 10‑year masterplan that covers 85 million square feet of land. Of this, 6.5 million square feet are earmarked for green areas and public land, underscoring the developer’s commitment to sustainability and community spaces. The masterplan allocates 60 percent of the area for residential use, while the remaining space will host commercial precincts, exclusive waterfront enclaves, and family‑focused neighbourhoods.

Al Abdouli described the project as “one of the biggest master plans that ever launched in the history of Ras Al Khaimah.” The development sits on Al Marjan Island, a 2.7‑million square‑meter man‑made archipelago composed of four islands. The island will also host the region’s first integrated gaming resort, Wynn Al Marjan, which has seen its opening date moved from March 2027 to September 2027.

Infrastructure and Supply‑Chain Challenges

While the overall infrastructure projects on the island remain “firmly on track,” Al Abdouli acknowledged that supply‑chain constraints have impacted delivery timelines for some components. Despite these hurdles, the developer remains confident that the project will stay on schedule.

The Marjan Digital Universe platform, introduced at the Arabian Travel Market, is designed to provide potential investors with a virtual tour of the evolving landscape. By enabling interactive engagement, the platform aims to showcase the various masterplans and developments that will shape Ras Al Khaimah’s future.

What’s Next for Marjan Beach?

With the first phase of earthwork nearing completion, the next steps involve the construction of foundational infrastructure, including roads, utilities, and public amenities. Once the groundwork is laid, developers will begin building the mixed‑use precincts, starting with residential units and moving into hospitality and commercial spaces.

As the project progresses, stakeholders will continue to monitor supply‑chain dynamics and adjust timelines accordingly. The completion of the first phase is expected to accelerate the overall development schedule, bringing the vision of a vibrant waterfront community closer to reality.

Why This Matters

Marjan Beach represents a transformative investment in Ras Al Khaimah’s coastal economy, promising new housing, tourism, and business opportunities. The project’s emphasis on green space and public land also highlights a commitment to sustainable urban development.

Key Takeaways

  • First phase of Marjan Beach earthwork to finish in two months.
  • Project spans 85 million sq ft, with 6.5 million sq ft dedicated to green and public land.
  • Major developers—Wasl, Omniyat, Beyond—have secured plots.
  • Wynn Al Marjan gaming resort opening moved to September 2027.
  • Marjan Digital Universe offers virtual tours of the masterplan.
  • Infrastructure remains on schedule despite supply‑chain challenges.

Frequently Asked Questions

  • When will Marjan Beach’s first phase be completed? The earthwork for the first phase is expected to finish within the next two months.
  • What is the Marjan Digital Universe? It is a virtual platform that allows investors to explore Marjan’s projects online.
  • Which developers are involved? Key players include Wasl, Omniyat, and Beyond.
  • What’s the timeline for Wynn Al Marjan? The resort’s opening has been rescheduled to September 2027.
  • How much land is set aside for green space? 6.5 million square feet of the 85 million square feet are designated for green areas and public land.

Why it matters

Marjan Beach’s development will reshape Ras Al Khaimah’s coastline, creating new residential, commercial, and leisure opportunities while promoting sustainable urban growth.

Key points

  • First phase earthwork to finish in 2 months
  • 85 million sq ft masterplan with 6.5 million sq ft green space
  • Key developers secured plots: Wasl, Omniyat, Beyond
  • Wynn Al Marjan resort opening moved to Sept 2027
  • Marjan Digital Universe offers virtual tours
  • Infrastructure on track despite supply‑chain issues

Frequently asked questions

When will Marjan Beach’s first phase be completed?

The earthwork for the first phase is expected to finish within the next two months.

What is the Marjan Digital Universe?

It is a virtual platform that allows investors to explore Marjan’s projects online.

Which developers are involved?

Key players include Wasl, Omniyat, and Beyond.

What’s the timeline for Wynn Al Marjan?

The resort’s opening has been rescheduled to September 2027.

How much land is set aside for green space?

6.5 million square feet of the 85 million square feet are designated for green areas and public land.

Reporting drawn from

More from World

Felo News, House 42, Bridge Colony, Kot Lakhpat, Lahore, Pakistan
+92 308 4354717 · felopronews@gmail.com